US Army Corps of Engineers Coastal Storm Risk Management (CSRM) Project

Start Date: July 3, 2024 and to last 4 months

Projected End Date: October 1, 2024

Project Area: The Project will extend from the northern end of Gamble Rodgers State Recreation Area to 7th Street North.  The planned construction time is 3 months and will be built from south to north along the coast.

Project Details:
US Army Corps of Engineers - Flagler County Coastal Storm Risk Management Project 2024

Completed Dune Restoration Projects - 2023

  • January 23 - March 1st: FEMA (Category G) Dune Restoration project in response to Hurricane Dorian - Completed.
  • March 1 - March 23: Washington Oak Gardens State Park Dune Restoration Project - Completed.
  • March 27 - May 28: Painter's Hill and Beverly Beach FDEP funded Dune Restoration Project - Completed.
  • June 1 - June 30: S. Hammock Dune Restoration Project -Completed.
  • FEMA Category B Emergency Dune Restoration Project: 
    Phase 1July 5 - September 21: Dune restoration from the Hammock Beach Resort through the northern section of Hammock Dunes community (to tie into the previously completed S. Hammock Dune project). -Completed
    Phase 2: September 18 - December 1: Dune restoration will be from River to the Sea Preserve boardwalk to the northern boundary of Washington Oak Gardens State Park. -Completed

Beach Management Study - Graphic of Planned Projects Draft - TBD based on Approval from BOCC

 